Municipal & County | Public & Private Utility | Transportation and Infrastructure Projects

D

back to projects

Water Infrastructure Upgrades Phase I, Hoboken, NJ
Client: CITY OF HOBOKEN

The City of Hoboken owns the drinking water transmission and distribution system, and this system is managed, operated, and maintained by Veolia. The City hired ENGenuity and another Engineering Consultant to design the upgrades for eight (8) areas totaling 7,035 LF with curb-to-curb resurfacing and complete street design. The project is funded through low-interest loans through the New Jersey Environmental Infrastructure Trust Program. The eight segments totaling 7,035 linear feet are as follows:

  1. Jefferson Street between 8th Street and 9th Street – approximately 450 linear feet
  2. Bloomfield Street between 2nd Street and 4th Street – approximately 1,000 linear feet
  3. Garden Street between 3rd Street and 5th Street – approximately 850 linear feet
  4. Monroe Street between 3rd Street and 4th Street – approximately 950 linear feet
  5. Monroe Street between 8th Street and 11th Street – approximately 1,400 linear feet
  6. Jefferson Street between 10th Street and 11th Street – approximately 450 linear feet
  7. Garden Street between 12th Street and 14th Street – approximately 810 linear feet
  8. Garden Street between Observer Highway and 2nd Street – approximately 1,125 linear feet

This $5M project completed the construction phase in the Winter of 2020, and the construction inspection was handled by ENGenuity as a sub-consultant.