Client: CITY OF HOBOKEN
The water main replacement phase of this project was completed in Summer 2024 and following that project ENGenuity was authorized to design the roadways listed below that comprised the Phase 2 water infrastructure project:
- Madison Street between 4th Street and 6th Street
- Grand Street between 3rd Street and 8th Street
- Jefferson Street between Newark Street and 1st Street
- 7th Street between Adams Street and Grand Street
- Adams Street between 8th Street and 9th Street
- 8th Street between Adams Street and Jefferson Street
The City requested that ENGenuity included the following intersections as part of the roadway portion of the Phase 2 project: 7th Street and Monroe Street intersection, 7th Street and Madison Street intersection, and 5th Street and Monroe Street intersection.
MORE
ENGenuity designed curb-bumpouts, installation of bioswales/rain gardens, installation of a Class 1 protected bike lane on Grand Street, installation of stormwater detention structures (green/grey tanks), inclusion of new ADA concrete ramps; mill and paving, and new striping. The project included applying for I-Bank Clean Water funding. The $3M project was advertised for Fall 2024, with construction commencing shortly thereafter. ENGenuity handled full-time construction observation.