JCMUA Aqueduct Loop Phases 2-5
Client: : JERSEY CITY MUNICIPAL UTILITIES AUTHORITY (JCMUA)

The goal of this project is to continue the installation of an aqueduct main (30” Water Main Pipe) along the southeastern portion of the City to continue the process of interconnecting the current aqueduct loop to all portions of the City. Phase 2, includes the area along Jersey Avenue from Aetna Street to Grand Street.

MORE

Phase 3: Regent Street (Jersey Avenue to Tidewater Street) Project

Phase 3 includes the area along Regent Street between Jersey Avenue and Tidewater Street. It is a three-block area that will include the following items as part of the overall scope:

  • Design a 30″ main on Regent Street from Jersey Avenue to Tidewater Street.
  • Coordinate outreach to notify properties of change in operating pressure.
  • Design new or expand existing cathodic protection on 30″ main.
  • Reposition temporary pressure zone division valves.

Phase 4: Tidewater St (Regent St to Morris Blvd) and Morris Blvd (Tidewater St to Marin Blvd) Project

Phase 4 includes the area along Tidewater Street from Regent Street to Morris Boulevard, and along Morris Boulevard from Tidewater Street to Marin Boulevard. It is a long four-block area that will include the following items as part of the overall scope:

  • Design a 30″ main on Tidewater Street (Regent St to Morris Blvd) and Morris Boulevard (Tidewater St to Marin Blvd).
  • Design new or expand existing cathodic protection on 30″ main.
  • Reposition temporary pressure zone division valves.

Phase 5: Morris Street (Greene St to Van Vorst St) Project

Phase 5 includes the area along Morris Street from Greene Street to Van Vorst Street. It is a three-block area that will include the following items as part of the overall scope:

  • Design a 30″ main on Morris Street between Greene St and Van Vorst St.
  • Reperform hydrostatic testing and disinfection of installed main between Van Vorst St and Marin Blvd.
  • Replace existing 6″ and 8″ CIP mains with new 12″ DIP main.
  • Coordinate outreach to notify properties of change in operating pressure.
  • Design new or expand existing cathodic protection on 30″ main.
  • Reposition temporary pressure zone division valves.