Bayonne Sewer System Upgrades
Client: VEOLIA

The City of Bayonne services a population of 70,000 and encompasses approximately 5.80 square miles. The City’s sanitary sewer system consists of:

  • 94.4 miles of gravity sanitary sewer mains (various sizes).
  • 11.2 miles of pressurized sewer force main.
  • Thirteen (13) pump stations, including the Oak Street Pumping Station and related facilities.

The existing sewer pipes at Avenue F and East 24th Street are experiencing major failures and collapses due to pipe age, degradation, and increased sewer flows resulting from new developments. The overall goal of the Sewer System Upgrades Project is to significantly improve the sewer system network and prevent service disruptions to Bayonne residents in the area of Avenue F between Mechanic Street and East 24th Street.

MORE

The project area covers the intersection and corridor of Avenue F from Mechanics Street to East 24th Street within city limits, encompassing existing sewer infrastructure:

  • Avenue F (between Mechanic St and E 24th St): existing 54″, 30″, and 18″ sewer mains.
  • Connecting streets (Mechanic St, E 23rd St, E 24th St to Avenue F): existing 12″ and 8″ sewer mains, typically located along sidewalks.

Project Scope
The project involves the following design criteria:

  • Replacement of approximately 600 linear feet of existing 18-inch diameter vitrified clay pipe (VCP) sanitary sewer main with new 18-inch diameter SDR 35 PVC pipe.
  • Replacement of approximately 1,000 linear feet of existing 8-inch diameter vitrified clay pipe (VCP) sanitary sewer main with new 12-inch diameter SDR 35 PVC pipe.
  • Replacement of approximately 1,200 linear feet of existing 12-inch diameter vitrified clay pipe (VCP) sanitary sewer main with new 12-inch diameter SDR 35 PVC pipe.
  • Rehabilitation of nine (9) existing sanitary manholes.
  • Installation of two (2) new sanitary manholes.
  • Reconnection of sewer laterals or catch basin laterals to new sewer piping.
  • Roadway restoration, including milling and paving, in compliance with the City of Bayonne Rules and Regulations.

Project Timeline and Budget

  • Design handled by ENGenuity in 2024/2025.
  • Estimated Project Cost: $2.5 million.